Started on April 202475 followers

Chief Street Upgrade

May 26, 2026 • 7:27 AM

Chief Street fly-through now complete

We’ve reached an exciting milestone for the Chief Street Upgrade, with the project fly-through now complete.


The fly-through brings the future vision for Chief Street to life, showing how the street will look and feel…

Flythrough Chief Street
Flythrough Chief Street

Chief Street Upgrade

December 22, 2025 • 12:50 AM

UNDERGROUNDING OF POWERLINES

SA Power Networks will begin undergrounding overhead powerlines between Second Street and Hawker Street (December 2025 - July 2026). Residents may notice work crews on site, with temporary traffic changes in place. There will be no power outages during this stag…

Admin-uploaded image

Chief Street Upgrade

July 17, 2025 • 5:05 AM

PROJECT UPDATE


Design Complete & Powerline Works Set to Begin

We’ve reached an exciting milestone. The design for Stage 2 of the undergrounding works (Ethelbert Square to Hawker Street) is now complete.


Undergrounding works …

Admin-uploaded image

Chief Street Upgrade

December 5, 2024 • 3:25 AM

POWERLINES & NEW STREET LIGHTS

Things are moving along on Chief Street, with Stage 1 of the powerlines undergrounded and new light poles currently being installed.


Stobie poles are also currently being removed, please keep clear of the trucks onsite while these are b…

Admin-uploaded image
Admin-uploaded image
1 / 2

Chief Street Upgrade

April 24, 2024 • 1:51 AM

UNDERGROUNDING POWERLINES - APRIL TO DECEMBER 2024

SA Power Networks is working with the City of Charles Sturt to underground powerlines along Chief Street between First Street and Third Street. Work includes undergrounding 515m of existing overhead powerlines and the removal of 21 stobie p…